Free template · Excel
Free Change Request Form Template (Excel)
Turn every "can we also…" into a decision instead of scope creep. Sort the request first, estimate its impact, give the client options, and record who approved what. The change log keeps a running total of the approved extra effort and timeline impact.
Download (.xlsx)
Works in Excel and Google Sheets · No sign-up · Updated
What's inside
- Change request: A one-page printable form: the request and its reason, sorting (defect, clarification or change request), impact on effort by role with automatic total and cost, timeline impact and risks, options A to D with a recommendation, the decision with approver and date, and follow-up checks.
- Change log: One row per request with type, effort, timeline impact, decision, and release. Totals show the number of requests, how many are open, and the approved effort and timeline impact.
- Request triage: Four questions that sort a request into a defect, a clarification, a change request, or gold plating, and what to do with each.
- How to use: The process from a new request to an updated plan.
Preview
Example rows from the Change log sheet:
| ID | Title | Effort (days) | Timeline impact (days) | Decision | Release |
|---|---|---|---|---|---|
| CR-01 | Add a cost centre column to the payroll export | 3 | 0 | Approved | v2.4 |
| CR-02 | Log in with company accounts (single sign-on) | 8 | 8 | Deferred | Later |
| CR-03 | Export timesheets to PDF as well as Excel | 2 | 2 | Open |
How to use it
- Sort the request with Request triage. Defects are fixed within the agreed scope.
- Copy the Change request sheet and fill in the request and the reason.
- Estimate the impact with the people who will build and test it.
- Give options (add, swap, defer, decline), recommend one, and get a written decision.
- Update the plan and status report, and add the request to the Change log.
To use it in Google Sheets, open Google Sheets, choose File, then Import, and upload the file. The dropdowns and formulas carry over.
The full guide behind this template: Scope Creep vs Change Request: How to Tell Them Apart.